<3. INSTALLATION>
3-1
IM 01E30D01-01EN
3. INSTALLATION
3.1 Piping Design Precautions
WARNING
Installationofthemagneticowmetermust
be performed by expert engineer or skilled
personnel. No operator shall be permitted to
perform procedures relating to installation.
IMPORTANT
Design piping correctly, referring to the following
topreventdamagetoowtubesandtoassure
accurate measuring.
(1) Location
IMPORTANT
Installtheowmeterinalocationwhereitis
not exposed to direct sunlight. The minimum
ambient temperature is limited by the minimum
uidtemperatureoftheowtube.Formore
information, refer to Chapter 11 “OUTLINE.” The
owmetermaybeusedinanambienthumidity
where the relative humidity ranges from 0 to
100%. However, avoid long-term continuous
operation at relative humidity above 95%.
(2) Noise Avoidance
IMPORTANT
Theowmetershouldbeinstalledawayfrom
electrical motors, transformers, inverters
and other power sources in order to avoid
interference with measurement.
(3) Required Lengths of Straight Runs
To maintain accurate measurement, see JIS B7554
“Electro Magnetic Flowmeters” which explains the
requirements for upstream piping conditions of
m
agneticowmeters.
The piping conditions we recommend as shown in
Figure 3.1.1 are based on JIS B7554 and on our
piping condition test data.
Wheninstallingtwoormoremagneticowmeters
on a single pipe, provide a run of at least 5D
between them.
Figure 3.1.1 Required Lengths of Straight Runs
*1: Do not install anything in the vicinity that may
interferewiththemagneticeld,inducedsignal
voltages,orowvelocitydistributionsofthe
owmeter.
*2: A straight run may not be required on the
downstreamsideoftheowmeter.However,
ifadownstreamvalveorotherttingcauses
irregularityordeviationinows,providea
straight run of 2D to 3D on the downstream
side.
*3: Highly recommend to mount valves on the
downstreamsidesothatdeviatedowsdonot
occurintheowtubeandtoavoidstartupfrom
an empty condition.
(4) Maintaining Stable Fluid Conductivity
IMPORTANT
Donotinstalltheowmeterwhereuid
conductivity tends to become uneven. If
chemicals are fed near the upstream side of a
magneticowmeter,theymayaffecttheow
rate’s indications. To avoid this situation, it is
recommended that the chemical feed ports be
locatedonthedownstreamsideoftheowmeter.
If it is unavoidable that chemicals must be fed on
theupstreamside,provideasufcientlengthof
straight run (approximately 50D) to ensure the
propermixtureofuids.
F0302.EPS
(Incorrect)
Upstream side
(Correct)
Downstream side
Figure 3.1.2 Chemical Injection